system: Virgin Trains West Coast Line
client: West Coast Traincare
provision: Willesden maintenance facility Silverlink upgrade
completed: 2005
This contract from West Coast Traincare was for the upgrading of their maintenance facility at Willesden for the Silverlink type 313 fleet. The work consisted of:
The project commenced in November 2004 and was completed by March 2005.
client: West Coast Traincare
provision: Willesden maintenance facility Silverlink upgrade
completed: 2005
This contract from West Coast Traincare was for the upgrading of their maintenance facility at Willesden for the Silverlink type 313 fleet. The work consisted of:
- Conversion of a pitted road
- Construction of driver walkways including lighting
The project commenced in November 2004 and was completed by March 2005.