system: Istanbul Metro
client: Acer Consultants
provision: Four Levant maintenance depot design development
completed: 1993
In 1993 Acer Consultants requested D&P to develop a design for Four Levant maintenance depot for the Istanbul Metro. The scope of works included the following functions:
client: Acer Consultants
provision: Four Levant maintenance depot design development
completed: 1993
In 1993 Acer Consultants requested D&P to develop a design for Four Levant maintenance depot for the Istanbul Metro. The scope of works included the following functions:
A Depot Requirement Report including:
- Definition of typical maintenance operations and representative work cycles
- Define typical workspace arrangements for the maintenance tasks
- Confirmation that the maintenance staff facilities and amenities as specified in a Parsons Brinkerhoff report were required, and if so, were adequate
- Identification of stabling and train movement requirements, including access from the main line
- Identification of the space requirements for the depot facilities, including a block diagram showing the requirements
- Identification of any specific structural/foundation requirements, such as drop table pits
- Identification of space requirements for the Control Centre
A Technical Specification including:
- A list and technical specification for all maintenance equipment required
- Bill of Quantities
- Cost estimates